Jump to a day
On jobsDrive (est)Gap 15m or lessGap 16-30mGap over 30mClock-in / out
Install
Install 1drive unavailable
07:03punch in16mdrive to 1st08:00first job14:19last job23mdrive from last15:21punch out8.3hclocked39m evening · shop +16m over
Install 1
Installdrive unavailable
07:10punch in—drive to 1st08:19first job13:01last job—drive from last14:05punch out6.9hclocked1.1h evening · shop +44m over
Fertilization
Casey Williams
Fertilization
06:21punch in18mdrive to 1st07:52first job13:26last job16mdrive from last13:26punch out7.1hclocked1.3hroute drive / day11 stops · 0m evening · shop +48m over
Gunner Findley
Fertilization
06:34punch in38mdrive to 1st07:29first job12:51last job6mdrive from last13:16punch out6.7hclocked3.0hroute drive / day6 stops · 19m evening
Humberto Lira
Fertilization
06:56punch in44mdrive to 1st08:01first job13:42last job34mdrive from last15:21punch out8.4hclocked2.0hroute drive / day10 stops · 1.1h evening
Mowing
Andrew Zawadzkitimes from stop taps
06:30punch in14mdrive to 1st07:22first job15:44last job11mdrive from last16:11punch out9.7hclocked13 stops · 16m evening · shop +13m over
06:35punch in33mdrive to 1st07:31first job14:47last job0mdrive from last15:04punch out8.5hclocked3.0hroute drive / day13 stops · 17m evening
Andrew Zawadzki
Mowingtimes from stop taps
08:09punch in13mdrive to 1st10:49first job16:48last job17mdrive from last17:27punch out9.3hclocked1.7hroute drive / day14 stops · 22m evening · shop +122m over
Gap = clock-in to first stop (or last stop to clock-out) minus the estimated drive, straight-line at 35 mph. Hover any bar segment for the exact times. Indirect = paid man-hours minus on-the-job man-hours for the same days. Data for a day completes about 5:30 the next morning. Revenue produced (headline) is the full RG-produced total for the period; the per-tech cards below show only crew-tapped production, so they sum a little lower.